Einde inhoudsopgave
Convention on the contract for the international carriage of goods by road
Article 19
Geldend
Geldend vanaf 02-07-1961
- Bronpublicatie:
19-05-1956, Trb. 1957, 84 (uitgifte: 24-06-1957, kamerstukken/regelingnummer: -)
- Inwerkingtreding
02-07-1961
- Bronpublicatie inwerkingtreding:
24-05-1961, Trb. 1961, 48 (uitgifte: 01-01-1961, kamerstukken/regelingnummer: -)
- Vakgebied(en)
Internationaal privaatrecht / Bijzondere onderwerpen
Verbintenissenrecht / Aansprakelijkheid
Vervoersrecht / Wegvervoer
Delay in delivery shall be said to occur when the goods have not been delivered within the agreed time-limit or when, failing an agreed time-limit, the actual duration of the carriage having regard to the circumstances of the case, and in particular, in the case of partial loads, the time required for making up a complete load in the normal way, exceeds the time it would be reasonable to allow a diligent carrier.