Einde inhoudsopgave
Principles of European Contract Law
Artikel 1:304 Computation of Time
Geldend
Geldend vanaf 01-01-1999
- Redactionele toelichting
Bron: frontpage.cbs.dk/law/commission_on_european_contract_law. De datum van publicatie is gezet op 01-01-1999.
- Bronpublicatie:
01-01-1999, Internet 1999, 000 (uitgifte: 01-01-1999, kamerstukken/regelingnummer: -)
- Inwerkingtreding
01-01-1999
- Bronpublicatie inwerkingtreding:
01-01-1999, Internet 1999, 000 (uitgifte: 01-01-1999, kamerstukken/regelingnummer: -)
- Vakgebied(en)
EU-recht / Bijzondere onderwerpen
Verbintenissenrecht / Overeenkomst
(1)
A period of time set by a party in a written document for the addressee to reply or take other action begins to run from the date stated as the date of the document. If no date is shown, the period begins to run from the moment the document reaches the addressee.
(2)
Official holidays and official non-working days occurring during the period are included in calculating the period. However, if the last day of the period is an official holiday or official non-working day at the address of the addressee, or at the place where a prescribed act is to be performed, the period is extended until the first following working day in that place.
(3)
Periods of time expressed in days, weeks, months or years shall begin at 00.00 on the next day and shall end at 24.00 on the last day of the period; but any reply that has to reach the party who set the period must arrive, or other act which is to be done must be completed, by the normal close of business in the relevant place on the last day of the period.