Principles of European Contract Law
Artikel 8:103 Fundamental Non-Performance
Geldend
Geldend vanaf 01-01-1999
- Redactionele toelichting
Bron: frontpage.cbs.dk/law/commission_on_european_contract_law. De datum van publicatie is gezet op 01-01-1999.
- Bronpublicatie:
01-01-1999, Internet 1999, 000 (uitgifte: 01-01-1999, kamerstukken/regelingnummer: -)
- Inwerkingtreding
01-01-1999
- Bronpublicatie inwerkingtreding:
01-01-1999, Internet 1999, 000 (uitgifte: 01-01-1999, kamerstukken/regelingnummer: -)
- Vakgebied(en)
EU-recht / Bijzondere onderwerpen
Verbintenissenrecht / Overeenkomst
A non-performance of an obligation is fundamental to the contract if:
- (a)
strict compliance with the obligation is of the essence of the contract; or
- (b)
the non-performance substantially deprives the aggrieved party of what it was entitled to expect under the contract, unless the other party did not foresee and could not reasonably have foreseen that result; or
- (c)
the non-performance is intentional and gives the aggrieved party reason to believe that it cannot rely on the other party's future performance.