Einde inhoudsopgave
Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management
Article 9 Operation of facilities
Geldend
Geldend vanaf 18-06-2001
- Bronpublicatie:
05-09-1997, Trb. 1999, 164 (uitgifte: 03-09-1999, kamerstukken/regelingnummer: -)
- Inwerkingtreding
18-06-2001
- Bronpublicatie inwerkingtreding:
22-06-2001, Trb. 2001, 111 (uitgifte: 01-01-2001, kamerstukken/regelingnummer: -)
- Vakgebied(en)
Milieurecht / Straling
Milieurecht / Energie
Energierecht (V)
Each Contracting Party shall take the appropriate steps to ensure that:
- (i)
the licence to operate a spent fuel management facility is based upon appropriate assessments as specified in Article 8 and is conditional on the completion of a commissioning programme demonstrating that the facility, as constructed, is consistent with design and safety requirements;
- (ii)
operational limits and conditions derived from tests, operational experience and the assessments, as specified in Article 8, are defined and revised as necessary;
- (iii)
operation, maintenance, monitoring, inspection and testing of a spent fuel management facility are conducted in accordance with established procedures;
- (iv)
engineering and technical support in all safety-related fields are available throughout the operating lifetime of a spent fuel management facility;
- (v)
incidents significant to safety are reported in a timely manner by the holder of the licence to the regulatory body;
- (vi)
programmes to collect and analyse relevant operating experience are established and that the results are acted upon, where appropriate;
- (vii)
decommissioning plans for a spent fuel management facility are prepared and updated, as necessary, using information obtained during the operating lifetime of that facility, and are reviewed by the regulatory body.