Principles of European Law on Service Contracts (PELSC)
Artikel 2:110 Resort to Other Remedies
Geldend
Geldend vanaf 01-10-2005
- Redactionele toelichting
De dag van de datum van publicatie is gezet op 01.
- Bronpublicatie:
01-10-2005, Internet 2005, www.sgecc.net (uitgifte: 01-10-2005, kamerstukken/regelingnummer: -)
- Inwerkingtreding
01-10-2005
- Bronpublicatie inwerkingtreding:
01-10-2005, Internet 2005, www.sgecc.net (uitgifte: 01-10-2005, kamerstukken/regelingnummer: -)
- Vakgebied(en)
Verbintenissenrecht / Overeenkomst
(1)
The client may resort to other remedies as provided in this Article, if
- (a)
the constructor refuses to cure because the client is not entitled to ask for cure under Article 2:109(1); or
- (b)
the constructor is unable or fails to cure according to Article 2:109(3).
(2)
The client may terminate the contract in accordance with Chapter 9, Section 3 PECL (Termination of the Contract) if the non-conformity is a fundamental non-performance according to Article 8:103(b) or (c) PECL (Fundamental Non-Performance).
(3)
The client may reduce the price in accordance with Article 9:401 PECL (Right to Reduce Price).
(4)
The client may claim damages under Chapter 9, Section 5 PECL (Damages and Interest), including the costs of repair or replacement.