The Energy Charter Treaty
Article 26 Settlement of disputes between an Investor and a Contracting Party
Geldend
Geldend vanaf 16-04-1998
- Bronpublicatie:
17-12-1994, Trb. 1995, 108 (uitgifte: 28-04-1995, kamerstukken/regelingnummer: -)
- Inwerkingtreding
16-04-1998
- Bronpublicatie inwerkingtreding:
27-03-1998, Trb. 1998, 78 (uitgifte: 01-01-1998, kamerstukken/regelingnummer: -)
- Vakgebied(en)
Milieurecht / Straling
Milieurecht / Energie
Energierecht (V)
1.
Disputes between a Contracting Party and an Investor of another Contracting Party relating to an Investment of the latter in the Area of the former, which concern an alleged breach of an obligation of the former under Part III shall, if possible, be settled amicably.
2.
If such disputes can not be settled according to the provisions of paragraph 1 within a period of three months from the date on which either party to the dispute requested amicable settlement, the Investor party to the dispute may choose to submit it for resolution:
- a)
to the courts or administrative tribunals of the Contracting Party party to the dispute;
- b)
in accordance with any applicable, previously agreed dispute settlement procedure; or
- c)
in accordance with the following paragraphs of this Article.
3
a)
Subject only to subparagraphs b) and c), each Contracting Party hereby gives its unconditional consent to the submission of a dispute to international arbitration or conciliation in accordance with the provisions of this Article.
b)
- (i)
The Contracting Parties listed in Annex ID do not give such unconditional consent where the Investor has previously submitted the dispute under subparagraph 2a) or b).
- (ii)
For the sake of transparency, each Contracting Party that is listed in Annex ID shall provide a written statement of its policies, practices and conditions in this regard to the Secretariat no later than the date of the deposit of its instrument of ratification, acceptance or approval in accordance with Article 39 or the deposit of its instrument of accession in accordance with Article 41.
c)
A Contracting Party listed in Annex IA does not give such unconditional consent with respect to a dispute arising under the last sentence of Article 10(1).
4.
In the event that an Investor chooses to submit the dispute for resolution under subparagraph 2 c), the Investor shall further provide its consent in writing for the dispute to be submitted to:
- a)
- (i)
The International Centre for Settlement of Investment Disputes, established pursuant to the Convention on the Settlement of Investment Disputes between States and Nationals of other States opened for signature at Washington, 18 March 1965 (hereinafter referred to as the ‘ICSID Convention’), if the Contracting Party of the Investor and the Contracting Party party to the dispute are both parties to the ICSID Convention; or
- (ii)
The International Centre for Settlement of Investment Disputes, established pursuant to the Convention referred to in subparagraph a)(i), under the rules governing the Additional Facility for the Administration of Proceedings by the Secretariat of the Centre (hereinafter referred to as the ‘Additional Facility Rules’), if the Contracting Party of the Investor or the Contracting Party party to the dispute, but not both, is a party to the ICSID Convention;
- b)
a sole arbitrator or ad hoc arbitration tribunal established under the Arbitration Rules of the United Nations Commission on International Trade Law (hereinafter referred to as ‘UNCITRAL’); or
- c)
an arbitral proceeding under the Arbitration Institute of the Stockholm Chamber of Commerce.
5
a)
The consent given in paragraph 3 together with the written consent of the Investor given pursuant to paragraph 4 shall be considered to satisfy the requirement for:
- (i)
written consent of the parties to a dispute for purposes of Chapter II of the ICSID Convention and for purposes of the Additional Facility Rules;
- (ii)
an ‘agreement in writing’ for purposes of article II of the United Nations Convention on the Recognition and Enforcement of Foreign Arbitral Awards, done at New York, 10 June 1958 (hereinafter referred to as the ‘New York Convention’); and
- (iii)
‘the parties to a contract [to] have agreed in writing’ for the purposes of article 1 of the UNCITRAL Arbitration Rules.
b)
Any arbitration under this Article shall at the request of any party to the dispute be held in a state that is a party to the New York Convention. Claims submitted to arbitration hereunder shall be considered to arise out of a commercial relationship or transaction for the purposes of article I of that Convention.
6.
A tribunal established under paragraph 4 shall decide the issues in dispute in accordance with this Treaty and applicable rules and principles of international law.
7.
An Investor other than a natural person which has the nationality of a Contracting Party party to the dispute on the date of the consent in writing referred to in paragraph 4 and which, before a dispute between it and that Contracting Party arises, is controlled by Investors of another Contracting Party, shall for the purpose of article 25(2)b) of the ICSID Convention be treated as a ‘national of another Contracting State’ and shall for the purpose of article 1(6) of the Additional Facility Rules be treated as a ‘national of another State’.
8.
The awards of arbitration, which may include an award of interest, shall be final and binding upon the parties to the dispute. An award of arbitration concerning a measure of a sub-national government or authority of the disputing Contracting Party shall provide that the Contracting Party may pay monetary damages in lieu of any other remedy granted. Each Contracting Party shall carry out without delay any such award and shall make provision for the effective enforcement in its Area of such awards.